Pakistan WHG project contracted by Sinoma-ec combined to the grid

January 29, the whole generating unit of Pakistan Cherat Cement CompanyCCCL3200 t/d cement line pure low temperature waste heat power plant 1×7MW unit, which is contracted by Sinoma Energy Conservation Company Ltd. , successfully started and combined to the grid on the same day.

 

The project started in April, 2009 and began commissioning on January 1, 2010.

 

Located in Northwest of Pakistan, CCCL was established in 1984. Its cement production capacity is 3200 t/d. The company affiliates to Pakistan Ghulam Farooque Group (GFG), which is one of the top 100 enterprises in Pakistan and mainly engaged in building materials manufacturing like cement production.

 